Branch Network Migration Plan

Plan the network migration of a 50-person branch with zero unplanned downtime.

The Scenario

A SA retailer is consolidating two branch offices into one new location. 50 staff, point-of-sale terminals, an in-branch CCTV system, and a credit card processing terminal must all be migrated within a weekend without disrupting Monday trading. The CIO wants a written migration plan before sign-off.

The Brief

Produce a complete migration plan covering the cutover weekend, a rollback strategy, and the communications plan. Make defensible assumptions about the existing infrastructure and document them.

Deliverables

  • A migration runbook with hour-by-hour activities for the cutover weekend (Friday close to Monday open), assigned roles, dependencies, and decision points
  • A rollback plan defining the latest acceptable rollback time and the criteria that would trigger it
  • A risk register with at least 8 migration-specific risks, each scored and mitigated
  • A communications plan covering staff, suppliers, the bank for the credit card terminal, and the building landlord

Submission Guidance

Real branch migrations fail because of the things nobody planned for: payment terminal certificates, courier deliveries on cutover Saturday, alarm system reconfiguration, and printer driver issues on Monday. Show that you have thought past the technical work to the operational reality.

Submit Your Work

Your submission is graded against the rubric on the right. If you pass, you get a public Badge URL you can share on LinkedIn. There is no draft save, so work offline first and paste your finished response here.

This appears on your public Badge.

0/20000 charactersMarkdown supported

One per line or comma separated. Up to 5 links.

By submitting, you agree your submission text, name, and evaluation will appear on a public Badge URL.